up to 95% work completed on the remaining 111 km. long Katra- Banihal section
IR is edging closer to connecting Kashmir Valley to the rest of the Railway network
Emphasize expediting the remaining work of the project.
Shri Shobhan Chaudhuri, General Manager, Northern Railway has carried out an intensive inspection of the USBRL project and other ongoing railway works in J& K on 05.07.2023 along with Shri S. P. Mahi, CAO/USBRL, Shri R. K. Hegde, Director/KRCL and a team of other senior officers from USBRL Project, KRCL and Firozpur Division.
Shri Chaudhuri commenced his inspection from Katra onwards by motor trolley up to tunnel T1 and thereafter conducted an exhaustive inspection and review of tunnel T1 at the site with USBRL officers, KRCL officers, and the agency. He directed all officers and staff to work in earnest ensuring all safety precautions and complete the work of the T1 tunnel, which is undoubtedly negotiating the most challenging geology of the Himalayas. During his inspection of the Anji Bridge, He appreciated the extremely good work being done on this.
He further conducted the Chenab bridge inspection and detailed motor trolley inspection from Chenab Bridge to Dugga station. He also directed that the target of the projects is sacrosanct and should be added to. He was appreciative of the good work done on the Chenab Bridge. He was pleased with ongoing works on the Bakkal- Dugga section, but at the same time emphasized expediting the electrical and S& T works of the project. He was appreciative that USBRL has been Pioneer in Indian Railways for undertaking the ROCs work (Rigid overhead catenary system). He had detailed discussions with the engineers of the agency executing the ROC’s work at Reasi and directed them to expedite this work as a top priority.
Shri S. P. Mahi, CAO, the USBRL project explained that out of the 272 km USBRL project, 161 Km of Railway track has already been commissioned. On the remaining 111 km. long Katra- Banihal section, the ongoing work is completed up to 95% in spite of all types of geological, topographical, and meteorological challenges. Work on the remaining portion is in full swing. Every day, Indian Railway is edging closer to connecting Kashmir Valley to the rest of the Railway network.