NH44 4 laning project: Div Com reviews progress on Nashri to Banihal stretch

Gadyal Desk by Gadyal Desk
29/12/2020
A A
FacebookTwitterWhatsappTelegram

Directs DC Ramban to expedite land acquisition, structure removal works

JAMMU, DECEMBER 29: Divisional Commissioner, Jammu, Sanjeev Verma today reviewed the progress of four lanning work on Nashri to Banihal stretch of Jammu- Srinagar National Highway here at a meeting.

Related posts

India’s Solodarity with people POJK

وادی کشمیر میں وقف اثاثوں کی صحیح نگرانی اور ترقی ناگزیر

19/04/2025

پاکستانی پروپیگنڈا وزیرِ اعظم نریندر مودی کے دورۂ کشمیر کے دوران: سوشل میڈیا کا تجزیہ

17/01/2025

The meeting was attended by Regional Officer NHAI, Hem Raj and other concerned officers, while Deputy Commissioner Ramban along with other concerned officers attended the meeting through video conferencing.

The Divisional Commissioner reviewed the progress on land acquisition cases pertaining to National Highway Nashri to Banihal stretch.

The Deputy Commissioner Ramban apprised the Div Com about the progress at various key construction sites  and informed that most of the land acquisition cases have been resolved, while those pending are also at different stages.

The Div Com sought details of land acquisition cases, structure removal, and disbursement of compensation and shifting of electricity towers.

The Div Com asked the DC Ramban to monitor the pace of work closely and expedite the pending land acquisition cases, structure removal for smooth execution of work on the vital road project.

While reviewing the progress on shifting of electricity towers, the concerned officers apprised the Div Com that the work is almost complete.

The Div Com asked Ramban administration to resolve the bottlenecks, if any and facilitate the executing agencies in smooth execution of work. “Expedite the progress on land acquisition, structure removal and resolve the bottlenecks which are hampering the work progress,” he directed. He also directed the NHAI to expedite the pace on the stretch where land acquisition has been completed.

Gadyal Desk
Gadyal Desk
Previous Post

Div Com reviews Republic Day-2021 arrangements

Next Post

COVID-19 KITS DISTRIBUTED BY POLICE BARAMULLA AMONGST BPL FAMILIES OF DISTRICT BARAMULLA

Related Posts

India’s Solodarity with people POJK
Home

وادی کشمیر میں وقف اثاثوں کی صحیح نگرانی اور ترقی ناگزیر

by Gadyal Desk
19/04/2025
0

وقف املاک نہ کسی مذہبی لیڈر کی ملکیت ہوتی ہے اور ناہی کسی خاص انجمن کی ملکیت ہے بلکہ یہ...

Read more

پاکستانی پروپیگنڈا وزیرِ اعظم نریندر مودی کے دورۂ کشمیر کے دوران: سوشل میڈیا کا تجزیہ

17/01/2025
THE CALL OF THE MOUNTAINS NORTH KASHMIR’S NEW FRONTIERS FOR ADVENTURE SEEKERS

گریز وادی کشمیر کی تہذیب اور کلچر کی پہنچان

09/01/2025
قاضی سلمان کو ڈائریکٹر، پی آئی بی سرینگر کے بطور ترقی سے نوازا گیا

قاضی سلمان کو ڈائریکٹر، پی آئی بی سرینگر کے بطور ترقی سے نوازا گیا

09/01/2025
بانڈی پورہ میں عوام کی بہادری: زخمی فوجیوں کی مدد سے کشمیریت کی مثال قائم

بانڈی پورہ میں عوام کی بہادری: زخمی فوجیوں کی مدد سے کشمیریت کی مثال قائم

05/01/2025
Next Post

COVID-19 KITS DISTRIBUTED BY POLICE BARAMULLA AMONGST BPL FAMILIES OF DISTRICT BARAMULLA

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

  • Contact
  • About us
  • Advertise
  • Careers
  • Privacy Policy
e-mail: [email protected]

© 2022 Gadyal - Designed and Developed by GITS.

No Result
View All Result
  • Home
  • Kashmir
  • Jammu
  • World
  • National
  • Sports
  • Article
  • ePaper

© 2022 Gadyal - Designed and Developed by GITS.