The first Hangor-class submarines were expected to be commissioned in 2022-23. The Pakistan Navy had to wait until April 30, 2026, when PNS Hangor was commissioned in China. The programme, hailed as Pakistan’s most ambitious naval modernisation effort, has run several years behind schedule.
Under the 2015 agreement, China was to build four submarines and Karachi Shipyard and Engineering Works (KS&EW) the other four. The first batch was due in 2022-23 and the Karachi-built boats by 2028. The first Chinese-built boat arrived years late.
The engine substitution added to the problem. The submarines were originally to use German MTU diesel engines, but Germany did not approve export licences, so the programme switched to China’s domestically produced CHD620. Replacing an engine is rarely a simple swap. It typically means revisiting machinery layout, electrical integration and cooling arrangements, followed by fresh testing.
Public sources do not show how much of the delay the engine change caused. Other factors have also been cited, including pandemic disruption, reported problems with the combat management system and fiscal constraints. Analysts nonetheless link the engine switch to the delay, and it raises a fair question about how well a substitute engine was integrated into a design built around a different one. Pakistan has accepted the arrangement, but accepting an engine on paper is not the same as proving it in service.
The bigger question is whether the replacement can deliver the performance expected of it. The CHD620 must work alongside the submarine’s other systems without affecting reliability while submerged. Any integration problem could mean more testing, modification and delay.
The outlook for the four boats being built in Pakistan is less reassuring. Steel was cut for the fifth submarine in December 2021, and the keel of the sixth was laid in February 2025. Local construction relies on technology transfer and KS&EW’s experience. With the programme already behind schedule, the Karachi-built boats are under strain, and delivery is now widely expected in the early 2030s.
The origin of the delays matters because a submarine’s systems must work together: propulsion, electrical machinery, navigation and combat systems. Delays in integrating and testing them mean a finished hull may still not be operational.
The cost to the Pakistan Navy goes beyond money and schedule. Every year of delay is another year without these underwater capabilities in the Arabian Sea.
Commissioning is also not the end of the story. The Hangor boats must prove themselves through sustained operations, and equipment faults, maintenance problems and integration issues tend to emerge only once boats are in service. Pakistan has waited years for these submarines and will wait longer to learn whether they are reliable. That China can deliver the boats is one question. Whether it can deliver reliable submarines is another.