DC Reasi reviews progress of R&B, allied sector projects

Gadyal Desk by Gadyal Desk
07/11/2023
A A
DC Reasi reviews progress of R&B, allied sector projects
FacebookTwitterWhatsappTelegram

REASI, NOVEMBER 06: To review the progress of developmental works taken up under R&B Sector in the District during financial year 2023-24, a meeting of concerned officers was held today here under the chairmanship of Deputy Commissioner Reasi, Vishesh Mahajan.

At the outset, the Deputy Commissioner took a comprehensive physical/financial review of targets with regard to infrastructure development, up-gradation works and the macadamization process undertaken by R&B.

Related posts

Sakeena Itoo reviews progress on SAMAGRA Shiksha interventions across J&K

Sakeena Itoo reviews progress on health projects across Kashmir division

01/07/2025
LG’s upcoming visit to Baramulla; DC chairs preparatory meeting

DC B’la reviews progress under Aspirational Distt Prog

01/07/2025

The R&B functionaries apprised the DC about the present status of major developmental works and macadamization process through a detailed PowerPoint presentation.

After reviewing the ongoing works taken up in the current year by R&B and other allied sectors, the Deputy Commissioner directed the stakeholder departments to expedite the pace of work on each project to ensure their timeline completion so that people are benefitted at large.

Deputy Commissioner directed XEN Mahore to speed up the pace of execution by working in double shifts to complete the projects before the onset of severe winters/ snowfall. He exhorted the concerned Officers to monitor the progress of works on a daily basis.

To accelerate the completion of the vital road project connecting Kanda to Ransoo, the DC directed the Executive Engineer Public Works Department (PWD) to execute the work in double shift .This decision aims to ensure the timely completion of the road, particularly for the enhancement of pilgrimage, as number of pilgrims from different states visit Shiv Khori Shrine.

ADDC Jyoti Slathia, Joint Director Planning Sunita Kanchan, SE R&B Reasi, Xens PWD Katra, Reasi and Mahore and other concerned officers were present in the meeting.

Gadyal Desk
Gadyal Desk
Previous Post

DDC Chairperson Ramban kick starts work on road projects in sub- division Gool

Next Post

CS review progress of implementation of Jal Jeevan Mission (JJM)

Related Posts

Sakeena Itoo reviews progress on SAMAGRA Shiksha interventions across J&K
Srinagar

Sakeena Itoo reviews progress on health projects across Kashmir division

by Gadyal Desk
01/07/2025
0

Srinagar : Minister for Health and Medical Education, Social Welfare and Education, Sakeena Itoo, on Monday chaired a meeting at...

Read more
LG’s upcoming visit to Baramulla; DC chairs preparatory meeting

DC B’la reviews progress under Aspirational Distt Prog

01/07/2025
DC Pulwama inspects Polling Stations of Assembly Constituency 32 Pampore

DC Pulwama reviews JK Sehat App registration progress in the Distt

01/07/2025
Focus on timely resolution of public issues: Javid Dar to officials

Javid Dar inaugurates JKRTC Bus Service from Zaloora to Srinagar

01/07/2025

DC Shopian inspects work of rural development projects at Keller

01/07/2025
Next Post
CS review progress of implementation of Jal Jeevan Mission (JJM)

CS review progress of implementation of Jal Jeevan Mission (JJM)

  • Contact
  • About us
  • Advertise
  • Careers
  • Privacy Policy
e-mail: [email protected]

© 2022 Gadyal - Designed and Developed by GITS.

No Result
View All Result
  • Home
  • Kashmir
  • Jammu
  • World
  • National
  • Sports
  • Article
  • ePaper

© 2022 Gadyal - Designed and Developed by GITS.